环氧防静电地坪施工基面要求
环氧防静电地坪施工基面要求
Requirements for Construction Base Surface of Epoxy Antistatic Floor
环氧抗静电地坪涂料的施工和其他环氧地坪涂料的施工,如基础处理和封闭底漆层,是相同的,但环氧抗静电地坪涂料比其他环氧地坪涂料要多.环氧抗静电地板涂料的涂装顺序是:密封底漆层、抗静电铜网层、抗静电涂料砂浆层、抗静电腻子层和抗静电涂料层.
The construction of epoxy antistatic floor coatings is the same as that of other epoxy floor coatings, such as basic treatment and sealing primer layer, but there are more epoxy antistatic floor coatings than other epoxy floor coatings. The sequence of coating of epoxy antistatic floor coatings is: sealed primer layer, antistatic copper mesh layer, antistatic coating mortar layer, antistatic coating layer. Electrostatic putty layer and antistatic coating layer.
项目简介:本项目施工场地属于生产笔记本电脑的生产车间.工厂的地板要求所有的封闭、防静电和清洁,地板和生产设备及人员都有防静电的要求.因此,有必要通过防静电地板将静电引入接地系统,以快速消除静电.
Project introduction: The construction site of this project belongs to the production workshop of notebook computers. The floor of the factory requires all closure, anti-static and clean, and the floor and production equipment and personnel have anti-static requirements. Therefore, it is necessary to introduce static electricity into the grounding system through anti-static floor in order to eliminate static electricity quickly.
避免在人体或产品中堆积,对人体造成伤害或损坏产品质量.地面面积为6500.我们需要走叉车.经工程技术人员现场检查,得到方案,采用2mm环氧抗静电自整平地坪涂料.
Avoid accumulating in human body or products, causing harm to human body or damage to product quality. The surface area is 6500. We need to use forklift truck. After on-site inspection by engineers and technicians, we get the scheme, using 2mm epoxy anti-static self-leveling floor coating.
对于网站的要求,网站必须关闭,不需要交叉操作.环境温度的空气相对湿度必须小于75%,地面温度高于露点温度3摄氏度.
For website requirements, the website must be closed without cross-operation. The relative humidity of air at ambient temperature must be less than 75%, and the ground temperature must be 3 degrees Celsius higher than dew point temperature.
规划安排:施工前制定施工计划,划分工期,提前安排好材料、设备各阶段、人员到位施工材料准备好:必须严格按照a和B组分的比例混合,搅拌材料充分搅拌,根据施工速度调整材料,避免一次性分配.过多,造成浪费.
Planning arrangement: Before construction, make construction plan, divide construction period, arrange materials, equipment stages in advance, and prepare construction materials in place: mix materials strictly according to the proportion of components a and B, mix materials adequately, adjust materials according to construction speed, avoid one-time distribution. Too much, cause waste.